4 FAQs about Dublin energy storage grid structure changes

Can new data centres connect to Ireland's Electricity Grid?

Photograph: Getty Images/iStockPhoto New data centres will only be able to connect to Ireland's electricity grid if they also generate and supply power to homes and businesses, the regulator that oversees the energy industry has ruled.

Why is EirGrid halting new data center connections in Dublin?

EirGrid's indefinite moratorium on new data center connections in Dublin (extended until 2028) underscores the severity of the crisis. With over 500,000 square feet of data center construction stalled due to insufficient power, the risk of rolling blackouts looms large.

Will Ireland's First fuel cell-powered data center rely on the grid?

An Irish-South Korean consortium, however, is trying a different approach by building Europe's first fuel cell-powered data center –– with no reliance on the grid –– in County Offaly. The partnership between Irish Lumcloon Energy and South Korean SK Ecoplant, will use solid oxide fuel cells to power the data center.

What is Ireland's Electricity storage policy framework?

The policy framework is a first of kind policy, which clarifies the key role of electricity storage in Ireland's transition to an electricity-led system, supporting Irelands 2030 climate targets, it may be considered as a steppingstone on Ireland's path to net zero carbon emissions.